DEGIRMEN WEIR VE HEPP

PROJECT LOCATION: ANTALYA AKSEKİ / DEGIRMEN RIVER
CLIENT: ERENLER ENERGY PRODUCTION AND TRADE CO. INC.
PURPOSE: ENERGY

PROJECT CHARACTERISTICS:
7 m High Concrete Gravity Weir Body Uncontrolled Overflow Spillway with 113.41 m3/s Capacity
1077.97 m Long Conveyance Channel
125.75 m Gross Head
6.80 m3/s Project Discharge
6.84 MW Installed Capacity
2 Horizontal Axis Francis Turbines
19.81GWh Annual Energy Production
In Operation Since 2013

Spillway Type: Uncontrolled Frontal Overflow Concrete Dam
Conveyance Channel Type: 1078 m Length, 3.60 m Diameter, Modified Horseshoe
Rotage Type/Dimensions:
Head Pond/ 8.0 x 53.75 m
Penstock: 338.40 m Length, 1.4 m Diameter

 

SCOPE OF SERVICES: (2011-2013)
Site Specific Seismic Risk Assessment
Final Design Revision
Detail Design Works
Periodical Site Visits & Reporting During Construction

 

 
  • DEĞİRMEN REGÜLATÖRÜ VE HES
  • DEĞİRMEN REGÜLATÖRÜ VE HES
  • DEĞİRMEN REGÜLATÖRÜ VE HES
  • DEĞİRMEN REGÜLATÖRÜ VE HES
 