PROJECT LOCATION: ORDU/BALDIRAN RIVER
CLIENT: GENERAL ENERGY GENERATION CO. INC.
PURPOSE: ENERGY

PROJECT CHARACTERISTICS:

POWER PLANT:
5.1 m High Concrete Gravity Weir Body
4125 m Long Conveyance Channel
162.70 m Gross Head
6.127 MW Installed Capacity
2 Horizontal Axis Francis Turbines
13.987 GWh Annual Energy Production
In Operation Since 2014

SCOPE OF SERVICES: (2011-2014)
Feasibility and Planning Studies
Topographical Site Survey
Geological Site Investigations
Site Specific Seismic Risk Assessment
Final Design Works
Preparation of Technical Specifications
Consultancy for EM Equipment Selection
Detail Design Works
Periodical Site Visits & Reporting During Construction
Support and Attendance for Construction
Progress Meetings

 

30 m deep piles were implemented at weir body due to poor foundation conditions.

 
  • GENERAL REGÜLATÖRÜ VE HES
  • GENERAL REGÜLATÖRÜ VE HES
  • GENERAL REGÜLATÖRÜ VE HES
  • GENERAL REGÜLATÖRÜ VE HES
 
Erges Consulting Inc.
Harbiye Mah. Tavuskuşu Cad. No: 25/9 06460 Çankaya/Ankara, TURKEY • T: +90 312 479 26 06 • F: +90 312 479 26 08 • e-mail: info@erges.com.tr

Web Design: AdaNET